A large-scale section of the M80 Ring Road Upgrade required the
coordinated delivery of critical road safety infrastructure across
a live freeway environment. Works were staged over two years,
integrating multiple safety systems while maintaining live traffic
conditions and strict compliance with VicRoads standards.
Client: CPB Contractors
Product: Road & Asset Solutions. Signage, Linemarking, Guardrails & Crash Cushions
Completed: 2019-2021
Client problems
Delivering road safety infrastructure across a live freeway environment required staged installation, strict traffic management, and coordination across multiple systems and work zones.
Live Freeway Environment
Working on an operational freeway with high traffic volumes, requiring strict traffic management and compliance with TMP and TGS requirements
Long-Term Staged Delivery (2019-2021)
Managing a large-scale freeway upgrade over a 2-year period with evolving construction stages
Multi-Discipline Coordination
Simultaneous delivery of signage, barriers, and linemarking across multiple ramps and carriageways
Temporary vs Final Traffic Staging
Maintaining safe traffic flow during evolving construction stages
Financial & Program Efficiency
Large-scale scope with multiple interfaces
Ground & Service Constraints
Underground services and varying site conditions
Our solution
Integrated Road Safety Infrastructure
Delivered over a two-year period (2019–2021), the project aligned with construction staging and traffic management requirements, and involved the end-to-end delivery of road furniture and safety infrastructure:
• Supply and installation of gantry for overhead freeway guidance and lane management
• Installation of regulatory and directional signage
• Temporary linemarking for traffic staging and safety during construction
• Final linemarking (thermoplastic and waterborne) for permanent configuration
• Installation of guardrail systems, including transitions and terminals
• Installation of crash cushions / attenuators at critical impact points
Custom Operations
Works were staged and coordinated to manage live traffic conditions while aligning with evolving construction and traffic management requirements:
• Night works and controlled closures used to minimise disruption
• Sequenced installation aligned with construction staging across ramps and carriageways
• Temporary linemarking and safety measures implemented and updated as conditions changed, followed by final installations
• Pre-installation service locating and adaptive installation methods
This approach enabled safe, staged progression of works while maintaining traffic flow and adapting to changing site conditions across the project lifecycle.
Detailed results and impact
Improved Roadside Safety
Installation of compliant barriers, crash cushions, and signage systems improved roadside safety at critical impact points
Continuous Safe Navigation
Temporary and final linemarking ensured clear guidance for motorists throughout all construction stages
Efficient Project Delivery
Staged, coordinated installation reduced rework and supported overall program efficiency
Program & Cost Efficiency
Bundled delivery of road furniture elements improved resource utilisation and reduced mobilisation requirements
Long-Term Performance
Durable materials, including thermoplastic linemarking and galvanised barriers, support extended asset life and reduced maintenance requirements
Delivered to Specification
Delivered in line with VicRoads/DTP specifications for high-speed freeway environments